Summary of grid issues

Connection to the grid

The grid operator is obliged to connect to his system any power generating plant meeting the conditions for connection (Law on Electricity, Art. 50).

Renewable energy is given priority in the assessment of the grid connection application (Rule on Support Scheme, Art. 16 Par. 3).

Statutory provisions

  • Law on Energy (Ligj për energjinë)
  • Law on Electricity (Ligj për energjinë elektrike)
  • Rule on Support Scheme (Rregulla për Kushtet e Përgjithshme të Furnizimit me Energji)