Connection to the grid
Updated: 17.01.2019
There are several grid connection procedures. A plant operator is contractually entitled against the grid operator to the connection of renewable energy plants to the grid. The grid operator is obliged to enter into connection contracts (art. 9 par. 1, art. 11 par. 1 Law No. 3468/2006 in conjunction with art. 267, 268 GTSC).
Every operator of a renewable energy plant who is a contracting party to a connection contract is entitled to connection. Contracting parties can be only those producers of electricity from renewable sources that hold an electricity production licence (art. 3 Law No. 3468/2006). This licence is issued by the Ministry of Development for a period of 25 years and shall be approved by the Greek Regulatory Authority for Energy (RAE). This period may be extended by an additional 25 years (art. 3 par. 4 Law No. 3468/2006).
The obligated party is the transmission or distribution grid operator in charge (art. 12 par. 1 Law No. 3468/2006 in conjunction with art. 97 and art. 125 Law No. 3468/2011). The plant shall be connected at the economically and technically most suitable connection point.
Claims arise at the date of the conclusion of the contract. The contract shall be concluded according to a procedure specified by law, which applies to all applicants for connection (art. 268 par. 1, 2 GTSC).
Procedure
Process flow | For RES plants in the interconnected grid system, the procedure consists of the following steps:
For small-scale RES plants in the interconnected system, there is a simplified grid connection procedure. ”Small-scale RES plants” are defined as follows (art. 4 Law No. 3468/2010):
Those small-scale RES plants are not obliged to obtain production and installation licences (art. 4 Law No. 3468/2006). Apart from that, wind power installations of up to 20 kW, PV installations of up to 0.5 MW and PV installations on commercial buildings are also exempt from the obligation of implementing an EIA (art. 8 par. 13 Law No. 3468/2006). Except for the first two steps, the connection process for small plants is identical with the standard connection process described above. The only difference between the main grid system and non-interconnected islands is that on islands the authority responsible for the conclusion of agreements with the plant operators is HEDNO (art. 10 Law No. 3468/2006). However, LAGIE, the Greek Electricity Market Operator, can also conclude a contract (art. 10 Law No.4414/2016). In addition, ADMIE can make a connection offer to wind power plants in locations characterised as congested, under condition that the additional capacity of the plant will not exceed 20% of the projected aggregate power fed into the transmission system (art.8A Law No. 3468/2006). For small RES plants under a net metering scheme, the connection process is as follows:
For PV plants under the new (virtual) net metering scheme a similar but more detailed connection process is followed. The basic difference is that after the Connection Agreement is signed, the “Net-Metering Agreement” or the “Virtual Net-Metering Agreement” is signed (art. 8 Min. Res/F1/oik.175067). |
---|---|
Competent authority | Ministry of Environment and Energy (YPEN- MEE), Ministry of Economy, Development, and Tourism (MEDT), Public Power Corporation S.A. (PPC S.A.) - electric utility company, Regulatory Authority for Energy (RAE), Independent Power Transmission Operator (ADMIE), Hellenic Distribution Network Operator (HEDNO) |
Deadlines | Production licence: RAE is obliged to issue such a licence within 2 months and may consult the TSO (ADMIE) or the DSO (HEDNO) (art. 3 par. 2 Law No. 3468/2006 in conjunction with art. 118 par. 2h Law No. 4001/2011). Connection offer: The TSO (ADMIE) is obliged to make a connection offer within 4 months. This offer will be valid for 4 years (for large RES plants) or 6 months (for small-scale RES plants) (art. 8 par. 4 Law No. 3468/2006). The duration of the connection offer can be extended if the plant operator has submitted all the necessary applications. The extension varies between 18 - 24 months, depending on the grid connection works the grid operator has to carry out before the conclusion of the connection contract (art.8 par.4 Law No.3468/2006). Connection agreement: Connection agreement should be concluded within 3 months for small-scale RES plants and 6 months for large RES plants (art.11 par.4 Law No. 3468/2006). Operating licence: A plant operator shall apply for an operating licence, which will be issued within 20 days. Guarantee Letter: Guarantee letter is submitted to ADMIE within 2 months from the conclusion of a connection agreement (par. I.1.3 Law No.1453/2013). Finally, the date of connection of the plant to the grid depends on the contractual terms. During the contract negotiation process, each contracting party must meet various obligations and deadlines (art. 268 par. 1 GTSC). In addition, grid operators should realise the necessary grid connection works within 12 months since the connection agreement is signed (art.11. par.4 Law No.3468/2006). Wind parks above 150 MW, non-interconnected wind parks and RES plants of related capacity are excluded (art.11. par.4 Law No.3468/2006). For PV plants: If the PV plant is ready to be connected to the grid (if the RES operator applies for the activation of the connection), the plant should be connected to the grid within 3 months. If that deadline expires, the grid operator is obliged to compensate the RES operator 50% of the cost for the necessary grid connection works (stipulated in the connection contract), if the grid operator finally meets its obligation within 4 months from the submission of initial request; Otherwise, 100% of the contractually agreed cost for the necessary grid connection works (art. 14 par.3 Law No.3468/2006). For RES under the net-metering scheme: HEDNO examines the application and sends, within 1 month from the receipt of application, a Grid Connection Offer to the applicant, including a description of necessary works as well as related costs. The necessary connection works have to be finished by HEDNO within 1 month from signing the Connection Agreement. For PV tender: The tendered capacity must be connected to the grid within 18 months for category A and 24 months for category B PV installations (art.7 par. 9e Law No.4414/2016).
For the 2018 tenders, the following deadlines are set:
Furthermore, there is a number of provisions concerning plants on non-interconnected islands that are expected to be interconnected. For PV under the new net-metering scheme: HEDNO examines the application and sends, within 1 month from the receipt of application for net metering and 4 months for virtual net metering, a Grid Connection Offer to the applicant, including a description of necessary works as well as related costs. Connection Offer has a duration of 3 months. The necessary connection works have to be finished by HEDNO within one month from signing the Connection Agreement. The “Net-Metering Agreement” or the “Virtual Net-Metering Agreement” is signed within 15 days (art.8 Min. Res/F1/oik.175067). |