Grid issues in Bulgaria
Updated: 23.01.2019
Provisions in detail
Summary of grid issues
Connection to the grid | Plant operators are contractually entitled against the grid operator to the connection of a renewable energy plant to the grid (art. 116 par. 1 Energy Act). The right to priority connection was abolished by the latest amendment to the ERSA. |
---|---|
Use of the grid | Plant operators are contractually entitled against the grid operator to the purchase of their electricity (art. 18 par. 1 ERSA). |
Grid development | Plant operators are statutorily entitled against the grid operator to the expansion and development of the grid to enable the connection of a renewable energy plant to the grid (art. 116 par. 1, 3 Energy Act). |