Grid issues in Sweden
Updated: 17.01.2019
Provisions in detail
Summary of grid issues
Connection to the grid | The grid operator is statutorily obliged to connect electricity generation plants to the grid. Electricity from renewable sources is not given priority. |
---|---|
Use of the grid | Plant operators are statutorily entitled against the grid operator to use the grid. Electricity from renewable sources is not given priority. |
Grid development | The grid operator is statutorily obliged to expand the grids; however, the plant operators are not entitled to an expansion. Electricity from renewable energy sources is not given priority. |
Statutory provisions |
|