Connection to the grid

Updated: 10.01.2019

Author: Krzysztof Ignaciuk

Pursuant to RES-Act, Art. 116.3, the Order of 18/05/2017 determines the conditions and technical specifications of connecting renewable energy installations to heating networks

Procedure

Process flow

Upon fulfilling all criteria under Art. 5 of the Order of 18/05/2017, the operator of the installations submits an application for connection to the grid.

Deadlines

The grid operator must inform of the grid connection specifications within 30 days from the date of submission of the application.

Obligation to inform

No provisions

Priority to renewable energy

  • Priority to renewable energy
  • Non-discrimination

Distribution of costs

Consumers

Costs are borne by end users.

Distribution mechanism

No provisions

Poland

Basic information on legal sources