Feed-in tariff (EEG feed-in tariff)
Updated: 11.01.2019
Author: Tim Sternkopf
In Germany, small RES-E plants up to 100 kW are eligible for feed-in tariff as set out in the EEG 2017 (§ 19 par. 1 no. 2. And § 21 EEG 2017). The eligibility is coupled to the obligation of the plant operator to feed the electricity into the grid in the months for which he raises the claim of receiving the financial support.
Regardless of the size, all plants are eligible in exceptional cases for a feed-in tariff reduced by 20% (Ausfallvergütung), however no longer than 3 consecutive months and no more than 6 months within a calendar year (§ 21 par. 1 no 2 EEG 2017).
Eligible technologies
- Feed-in tariffs are granted only for electricity actually taken over by the grid operator (§ 21 par. 1 EEG 2017). The electricity may not be consumed in the direct surrounding of the power plant and needs to be transmitted through the grid (§ 21 par. 2 no 1 EEG 2017). Additionally, the plant is not allowed to participate at the electricity balancing market (§ 21 par. 2 no 2 EEG 2017).
Wind energy | Eligible.
|
---|---|
Solar energy | Eligible. Following additional technical requirements apply for solar installations: Solar plants must feature the technical capacity of being remote-controlled for the case of network overload and of reporting in real-time the actual feed-in power (§9 par. 1 and 2 EEG 2017). More solar installations, regardless of ownership, are considered one plant if they are on the same property or building and have been commissioned during 12 consequent calendar months. This consideration serves solely for the determination of the installed capacity (§9 par. 3 EEG 2017).
|
Geothermal energy | Eligible (§ 19 par. 1 EEG 2017). |
Biogas | Biogas is eligible for a feed-in tariff. (§ 19 par. 1 EEG 2017). According to the definition of the technology (§3 no. 11 EEG 2017), biogas is every gas won through the anaerobic digestion of biomass. § 3 no. 21 EEG 2017 specifies that biomass includes biogas, biomethane, landfill gas and gas from purification plants and from the biological degradable part of household and industrial waste. Biogas plant operators (except for plants using exclusively manure or waste) must additionally guarantee for plants commissioned after 31 December 2016 and fermentation residue storage build after 31 December 2011 that the hydraulic retention time at least 150 days is (§ 9 par. 5 EEG 2017).
|
Hydro-power | Eligible (§ 19 par. 1 EEG 2017). |
Biomass | Eligible (§ 19 par 1 EEG 2017).
|
Amount
- If the plant operator receives a regional certificate the feed-in tariff shall be reduced by EUR ct. 0.1 pro KWh (§ 53b EEG 2017)
- The feed-in tariff for tac except electricity shall be reduced by the amount of the tax exemption (§ 53c EEG 2017)
- The tariff level will be reduced to zero in case that
- a plant operator has not registered his plant as required by law (§ 52 par. 1 no. 1 EEG 2017 in conjunction with § 71 no. 1, EEG 2017; MaStRV). A plant operator has to register his plant at the Federal Network Agency (§ 6 par. 1 EEG 2017). This information to be submitted is defined by law and includes, for example, the name and contact details of the plant operator, the location of the power plant, the type of power plant, and its installed capacity (§ 6 par. 2 EEG 20172014);
- The tariff level will be reduced to the actual market value in the case that
- technical requirements are not met (§ 52 par. 2 no. 1 EEG 2017 in conjunction with § 9 par. 1, 2, 5 or 6 EEG 2017).
- the plant operator has switched between direct marketing of the electricity and the feed-in tariff without informing the grid operator (§ 52 par. 2 no. 2 EEG 2017);
- a plant operator breaches the prohibition of multiple sale electricity from renewable energy sources and mine gas (§ 52 par. 2 no. 5 EEG 2017 in conjunction with § 80 EEG 2017).
Wind energy |
|
---|---|
Solar energy | The amount of tariff depends on the site of production and the installed capacity.
|
Geothermal energy | €ct 25.2 per kWh (§ 45 EEG 2014) minus €ct 0.2 per kWh (§ 53 no. 1 EEG 2017) |
Biogas |
|
Hydro-power | €ct 3.47 – 12.40 per kWh (depending on plant size and date of commissioning) (§ 40 par. 1-4 EEG 2015) minus €ct 0.2 per kWh (§ 53 no. 1 EEG 2017). |
Biomass | €ct 5.71 – 13.32 per kWh (according to plant size) (§ 42 EEG 2017) minus €ct 0.2 per kWh (§ 53 no. 1 EEG 2017). |
Addressees
A plant operator is entitled to receiving a feed-in tariff according to the subsequent provisions of the law (§ 19 par. 1 EEG 2017) for the amount of energy fed into the grid. The grid operator is required to purchase, transfer and distribute the feed-in electricity (§ 11 EEG 2017). A plant operator is one, who, irrespective of the issue of ownership, uses a plant to generate electricity from renewable energy sources or from mine gas (§ 3 no. 2 EEG 2017). Grid operators are the operators of grid systems of all voltages for general electricity supply (§ 3 no. 36 EEG 2017).
Procedure
Process flow | Statutory law does not set out a formal application process. According to the EEG, the conclusion of a contract between the grid operator and the plant operator must not be made a condition for the payment of tariffs (§ 7 par. 1 EEG 2017). |
---|---|
Competent authority | The implementation of the EEG is monitored by the Federal Network Agency (§ 85 EEG 2017). The Act is evaluated by the Federal Government (§ 97 EEG 2017). |
Degression
For most technologies, the tariff levels will decrease in regular periods of time. New plants will receive the tariff level applicable on the day they are put into operation. This tariff level will apply for the entire payment period, i.e. for 20 years (§ 25 EEG). For some technologies, the percentages by which the tariff levels will decrease are set by law and are not subject to change. For other technologies the percentage by which the tariff levels will decrease depend on the amount of newly installed capacity.
Wind energy |
|
---|---|
Solar energy | The degression contains a basis degression rate of 0.5% every month (§ 49 par. 1 EEG 2017). The EEG 2017 has defined a target-corridor for the development of solar power of 2,500 MW per annum (§ 49 par. 2 EEG 2017). If the real development surpasses the corridor, the degression rate will be increased from 0.5% to up to 2.8% (§ 49 par. 2 EEG 2017). If the development of solar power goes below the targets of the corridor, the degression rate is reduced and, in extreme cases, the tariff rate will be even increased by up to 3% (§ 49 par. 3 EEG 2017). The current degression rates can be retrieved from: https://www.bundesnetzagentur.de/DE/Sachgebiete/ElektrizitaetundGas/Unternehmen_Institutionen/ErneuerbareEnergien/ZahlenDatenInformationen/EEG_Registerdaten/EEG_Registerdaten_node.html#doc732052bodyText5 (only in German). |
Geothermal energy | The degression rate will be 5% every year from 2021 (§ 45 par. 2 EEG 2017). |
Biogas | The degression rate for landfill gas sewage gas and mine gas is starting from 1.1.2018 by 1.5% annually (§ 41 par. 4 4 EEG 2017). The degression of biogas from other forms of biomass has a basis degression rate of 0.5% every 6 months (1 April and 1 October) starting from April 2017 (§ 44a EEG 2017). |
Hydro-power | The degression rate is 0.5% every year (§ 27 par. 1 no. 1 EEG 2017). |
Biomass | The degression for biomass has a basis degression rate of 0.5% every 6 months (1 April and 1 October) starting from April 2017 (§ 44a EEG 2017). |
Eligibility period
The tariff payment period is 20 years from the day of commissioning. For plants receiving a feed-in tariff the period may be expanded until 31 December of the 20th year (§ 25 EEG 2017).
Distribution of costs
Consumers | The costs of the feed-in tariff scheme are borne by the final consumers. |
---|---|
Distribution mechanism |
|