Grid access in Bulgaria
Updated: 26.11.2009Overview of access to the grid
| Statutory provisions |
|
|---|---|
| Connection to the grid | System operators are contractually entitled against the grid operator to the connection of a system for the generation of electricity from renewable sources to the grid (art. 116 par. 1 Energy Act). |
| Usage of the grid | System operators are contractually entitled against the grid operator to the purchase of their electricity (art. 16 par. 2 EEBG). |