Grid issues in Turkey

PDF

Updated: 23.01.2019

Author: Tim Sternkopf

Provisions in detail

Summary of grid issues

Connection to the grid

In Turkey, the connection to the grid occurs through a bidding procedure. The available connection regions and points are published by TEIAS on annual basis every 31 March of the year. A plant operator who wants to be connected to the grid needs a production license, clarify the connection details and arrange an agreement of the connection with TEIAS.

Statutory provisions

  • EMGR (Elektrik Piyasası Şebeke Yönetmeliği - Electric Market Grid Regulation) 
  • REMCUS Elektrik Piyasası Bağlantı ve Sistem Kullanım Yönetmeliği - Regulation of the Electricity Market Connection and Use of System 
  • YEK (Yenilenebilir Enerji Kaynakların Elektrikenerjisi Üretimi Amaclı Kullanıma İlişkin Kanun – Law on the Use of Renewable Energy Sources for Electricity Production) 
  • EEÜST (Elektrik Enerjisi Üretmek Amacıyla Aynı Bölge ve Aynı Kaynak İçin Yapılmış Birden Fazla Lisans Başvurusu Olması Halinde Seçim Yapılmasına İlişkin Usul ve Esaslar Hakkında Tebliğ - Notification Concerning the Choosing Procedure When There is More Than One Application for the Same Area and Same Resource) 
  • EPLY (Elektrik Piyasası Lisans Yönetmetmeliği – Regulation of Electricity Market Licenses)
  • EML (Elektrik Piyasasi Kanunu - Electricity Market Law No. 6446)

Turkey

Further information

  • T.C. Enerji Piyasası Düzenleme Kurulu (EPDK) - Energy Market Regulatory Authority (EMRA)