Connection to the grid
Updated: 17.01.2019
The holder of a "line network concession" (i.e. the grid operator) is obliged to connect renewable energy plants on reasonable terms unless there are special reasons (Chapter 3 § 6 par. 1; § 7 par. 1 Electricity Act).
Procedure
Process flow | The detailed procedure is set out in the Grid Code. Applicants have to submit an application for connection to the grid operator (Chapter 4 § 12 Electricity Act). Both parties then sign a grid connection agreement. Disputes about the grid operator's obligation are settled by the Inspectorate upon request (Chapter 3 § 6 par. 2; § 7 par. 2 Electricity Act). |
---|---|
Deadlines | The holder of a line network concession (i.e. the grid operator) is obliged to deal with applications for connection within a reasonable period of time (Chapter 4 § 11 Electricity Act). Furthermore, he shall develop a roadmap for the implementation of grid connection (Chapter 4 § 12 Electricity Act). |
Obligation to inform | The holder of a line network concession (i.e. the grid operator) is obliged to provide all information on his network tariff (including the terms and conditions for connection) on request within a reasonable period of time (Chapter 4 § 11 par. 1 and 2 Electricity Act). |