Grid development

Updated: 19.02.2019

Author: Stijn Anciaux

A contract may give rise to a claim for the expansion of the grid, if the expansion is necessary to connect a plant to the grid. This principle is based on the provisions on the connection charges, which may also include charges for a grid expansion (Art. 5 (6) Loi du 1er août 2007).

The persons entitled are plant operators connecting their plants to the grid (Art. 5 (1) Loi du 1er août 2007).
The person obligated is the grid operator (Art. 5 (1) Loi du 1er août 2007).

Procedure

Process flow

The grid operator shall inform the plant operator and the regulatory authority within 30 days about the extension works necessary to connect the plant (Art. 19 (3) Loi du 1er août 2007).

Distribution of costs

Plant operator

According to current legislation, the plant operator bears the cost of a grid expansion (Art. 5 (6) Loi du 1er août 2007). The grid operator may claim a reasonable amount of money for providing the necessary information on the measures required for the expansion of the grid (Art. 19 (3) Loi du 1er août 2007).