Grid issues in Lithuania
Updated: 19.12.2018
Provisions in detail
Summary of grid issues
Connection to the grid | The operators of renewable energy plants are entitled to priority connection to the grid. The grid operators are obliged to connect RES plants even if this is only possible by optimising, boosting or expanding the grid. A grid operator cannot set connection requirements other than those necessary for the proper, safe and reliable operation of an installation and the power system. |
---|---|
Use of the grid | RES plant operators are statutorily entitled against the grid operator to the access and transmission/distribution of all electricity from renewable sources offered. The grid operator shall ensure that electricity from renewable sources is given priority transmission/distribution. |
Grid development | After the conclusion of an agreement on the connection of a RES plant to the electricity grid with the RES plant operator, the grid operator shall, taking into account the current technical condition of the network, immediately take all reasonable steps to optimise, extend and/or reinforce the grid in order to ensure the safe and reliable receipt, transmission and distribution of electricity generated from renewable energy resources. However, according to the Law on Energy from Renewable Sources, the RES plant operator has no legal right to claim the development of the grid against the grid operator. |
Statutory provisions |
|