Grid development
Updated: 04.01.2019
In general, the grid operators shall act on their own responsibility and expand their grids to the extent necessary. If a grid operator fails to satisfy his obligation to expand the grid, the Ministry for Climate and Energy shall delegate responsibility for the expansion of the grid to Energinet.dk (§ 20 Act 1009/2018). The grid operator is not obliged to the plant operators to expand his grid.
Procedure
Process flow | The grid operator is statutorily obliged to expand the grid if the expansion is necessary to guarantee the efficient transmission of electricity (§ 20 Act 1009/2018). The target of increasing the use of renewable energy sources is given special attention whenever necessary (§ 21 Act 1009/2018). |
---|---|
Enforcement of claims | Statutory law does not give rise to an enforceable claim for grid expansion. |